For the period from 2000 to 2018 the company designed and launched eighteen complexes for processing of metallurgical wastes and ore enrichment with a capacity of 150tph to 375tph and the end product assortment in accordance with the requirements of the Customer.
December 2016
Raw materials: converter slag
Capacity: 350 tons per hour
Fractionary composure of the finished products:
Fractioned gravel: 0-10, 10-20, 20-40, 40-70 mm
Fractionary road metal: 0-10 mm, 10-100 mm, 100-300 mm, 300+ mm
December 2014
Raw materials: converter slag
Capacity: 200 tons per hour.
Fractionary composure of the finished products:
Fractionary road metal: 0-250 mm
Metal: 0-10 mm, 10-80 mm, 80-250 mm, 250+
September 2013
Raw materials: slag of electric steelmaking process (partial processing is fabricated)
Capacity: 300 tons per hour.
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm
December 2012
September 2010
Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)
Capacity: 375 tons per hour.
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm
Firebrick gritting, nonmagnetic metal
December 2009
Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)
Capacity: 375 tons per hour.
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm
Firebrick gritting, nonmagnetic metal
November 2009
Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)
Capacity: 150 tons per hour.
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm
Firebrick gritting, nonmagnetic metal
December 2008
Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)
Capacity: 150 tons per hour.
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm
Firebrick gritting, nonmagnetic metal
July 2008
Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)
Capacity: 300 tons per hour.
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+
Firebrick gritting, nonmagnetic metal
Raw materials: slag of open-hearth furnace process (partial processing is fabricated)
Capacity: 300 tons per hour
Term of construction and erection work: ~2.5 months.
General planner: «Giprostal», Kharkov
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm, + 250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+
Firebrick gritting
September 2007
Raw materials: slag of open-hearth furnace and electric steelmaking processes
Capacity: 250 tons per hour.
Term of construction and erection work: ~2 months.
General planner: Project Department «Donetskstal», Donetsk
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+
Nonmagnetic metal
Raw materials: slag of electric steelmaking process
Capacity: 300 tons per hour.
Term of construction and erection work: ~2 months.
General planner: SOE «Giproprom» Zaporozhye
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+
Nonmagnetic metal
March 2007
Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)
Capacity: 300 tons per hour.
Term of construction and erection work: ~3 months.
General planner: «Azovgipromez», Mariupol
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+
Firebrick gritting, nonmagnetic metal
December 2005
Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)
Capacity: 300 tons per hour.
Term of construction and erection work: ~2 months.
General planner: Project Department of MMC of a name of Ilyich, Mariupol
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+
Firebrick gritting, nonmagnetic metal
September 2005
Raw material: foundry waste
Capacity: 200 tons per hour.
Term of construction and erection work: ~1.5 months.
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+
May 2005
Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)
Capacity: 300 tons per hour.
Term of construction and erection work: ~2.5 months.
General planner: Project department of MMC of a name of Ilyich, Mariupol
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+
Firebrick gritting, nonmagnetic metal
July 2004
Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)
Capacity: 300 tons per hour.
Term of construction and erection work: ~3 months.
General planner: «Azovgipromez», Mariupol
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+
Firebrick gritting, nonmagnetic metal
Raw materials: rolling mill scrap
Capacity: 150 tons per hour.
Term of construction and erection work: ~3 months.
Fractionary composure of the finished products:
Nonmetallic fraction: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm
Raw material: slag of open-hearth furnace process (partial processing is fabricated)
Capacity: 200 tons per hour.
Term of construction and erection work: ~4 months.
General planner: “Giprostal”, Kharkov
Fractionary composure of the finished products:
Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm
Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm
Firebrick gritting