Slag of Open-hearth Furnace and Electric Steelmaking Processes Handling Complex 250 tph (Ukraine, 2007)

Customer: Closed Joint-Stock Company "Donetskstal" - Iron and Steel Works", 83062, Donetsk, Tkachenko str., 122 Ukraine

September 2007

Brief description

Features of the complex

Raw materials: slag of open-hearth furnace and electric steelmaking processes

Capacity: 250 tons per hour.

Term of construction and erection work: ~2 months.

General planner: Project Department «Donetskstal», Donetsk

Fractionary composure of the finished products:

Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

Nonmagnetic metal

In February of 2007, a contract for the delivery of a slag recycling complex was signed with Donetsk Metallurgic Plant.

The technological layout omits the sorting station, due to the particulars of Donetsk slag dumps. The changes also concerned the conveyor directions, due to the specific of available construction sites.

In the spring of 2007, the deliveries began.

In September of 2007, the complex began operations at the Donetsk Metallurgic Plant.