Metallurgical by-products processing

AMCOM L.L.C.  is an international company, which offers custom made solutions for processing metallurgical slag and scrap, enrichment of iron ore, and other equipment for the steel and coal industries. Since 2000 AMCOM L.L.C. designed and launched eighteen processing plants. We deliver Turn-Key projects including engineering, manufacturing, installation, maintenance, service and operation.

More

Finished slag processing products

Our projects

For the period from 2000 to 2018 the company designed and launched eighteen complexes for processing of metallurgical wastes and ore enrichment with a capacity of 150tph to 375tph and the end product assortment in accordance with the requirements of the Customer.

Download our Reference List

  1. Raw material: slag of open-hearth furnace process (partial processing is fabricated)

    Capacity: 200 tons per hour.

    Term of construction and erection work: ~4 months.

    General planner: “Giprostal”, Kharkov

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm

    Firebrick gritting

    More

  2. Raw materials: rolling mill scrap

    Capacity: 150 tons per hour.

    Term of construction and erection work: ~3 months.

    Fractionary composure of the finished products:

    Nonmetallic fraction: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm

    More

  3. Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)

    Capacity: 300 tons per hour.

    Term of construction and erection work: ~3 months.

    General planner: «Azovgipromez», Mariupol

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

    Firebrick gritting, nonmagnetic metal

    More

  4. Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)

    Capacity: 300 tons per hour.

    Term of construction and erection work: ~2.5 months.

    General planner: Project department of MMC of a name of Ilyich, Mariupol

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

    Firebrick gritting, nonmagnetic metal

    More

  5. Raw material: foundry waste

    Capacity: 200 tons per hour.

    Term of construction and erection work: ~1.5 months.

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

    More

  6. Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)

    Capacity: 300 tons per hour.

    Term of construction and erection work: ~2 months.

    General planner: Project Department of MMC of a name of Ilyich, Mariupol

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

    Firebrick gritting, nonmagnetic metal

    More

  7. Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)

    Capacity: 300 tons per hour.

    Term of construction and erection work: ~3 months.

    General planner: «Azovgipromez», Mariupol

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

    Firebrick gritting, nonmagnetic metal

    More

  8. Raw materials: slag of electric steelmaking process

    Capacity: 300 tons per hour.

    Term of construction and erection work: ~2 months.

    General planner: SOE «Giproprom» Zaporozhye

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

    Nonmagnetic metal

    More

  9. Raw materials: slag of open-hearth furnace and electric steelmaking processes

    Capacity: 250 tons per hour.

    Term of construction and erection work: ~2 months.

    General planner: Project Department «Donetskstal», Donetsk

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

    Nonmagnetic metal

    More

  10. Raw materials: slag of open-hearth furnace process (partial processing is fabricated)

    Capacity: 300 tons per hour

    Term of construction and erection work: ~2.5 months.

    General planner: «Giprostal», Kharkov

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm, + 250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

    Firebrick gritting

    More

  11. Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)

    Capacity: 300 tons per hour.

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+

    Firebrick gritting, nonmagnetic metal

    More

  12. Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)

    Capacity: 150 tons per hour.

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm

    Firebrick gritting, nonmagnetic metal

    More

  13. Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)

    Capacity: 150 tons per hour.

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm

    Firebrick gritting, nonmagnetic metal

    More

  14. Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)

    Capacity: 375 tons per hour.

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm

    Firebrick gritting, nonmagnetic metal

    More

  15. Raw materials: slag of open-hearth furnace and converter processes (partial processing is fabricated)

    Capacity: 375 tons per hour.

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm

    Firebrick gritting, nonmagnetic metal

    More

  16. Raw materials: iron ore (siderite magnetite)

    Capacity: 375 tons per hour.

    More

  17. Raw materials: slag of electric steelmaking process (partial processing is fabricated)

    Capacity: 300 tons per hour.

    Fractionary composure of the finished products:

    Fractionary road metal: 0-10 mm, 10-60 mm, 60-250 mm

    Metal: 0-10 mm, 10-60 mm, 60-250 mm, 250+ mm

    More

  18. Raw materials: converter slag

    Capacity: 200 tons per hour.

    Fractionary composure of the finished products:

    Fractionary road metal: 0-250 mm

    Metal: 0-10 mm, 10-80 mm, 80-250 mm, 250+

    More

  19. Raw materials: converter slag

    Capacity: 350 tons per hour

    Fractionary composure of the finished products:

    Fractioned gravel: 0-10, 10-20, 20-40, 40-70 mm

    Fractionary road metal: 0-10 mm, 10-100 mm, 100-300 mm, 300+ mm

    More

Capacity of complexes

2.5

million tons/year

on incoming raw materials

Return on investment

6

months including

construction and infrastructure

Terms of project realization

90/60

days for production

and assembly accordingly